"Better to be wise by the misfortunes of others than by your own."--Aesop
Getting an education about the process of rebuilding your home can be very expensive,
especially when those lessons come from looking out for your own money. Rebuilding after a
loss can be very exciting, creative, and fulfilling, but it can also seem like a never-ending
nightmare that bleeds you dry, both emotionally and financially. The difference between a good
and a bad experience comes down to two things:
1. How well prepared you are for the journey.
2. How resilient you are when things change.
Our mission in this article is to help you prepare for the rebuilding journey through six important
lessons. Remember that even in the best-planned projects, changes and surprises will occur.
Whether it's the weather, the contractors, the building department, or any of a zillion things that
can throw a wrench into your project, one thing is certain: things will change. Some people deal
well with change and find opportunities in the dynamics of the situation. For some, however, the
construction process with all its uncertainties only leads to disappointment and frustration. The
construction game is best played by those who have a clear vision of what they want, and, at the
same time, an open mind for the possibilities that will emerge.
Lesson 1: Do business with the right people. This is perhaps the single most important thing
that you can do to obtain the best outcome. Spend the time it takes to check references on those
you do business with. Surprisingly, bad contractors will sometimes refer you to past clients who
will tell you, "Don't hire that guy!" Just because a contractor gives you what looks like a nice list of
references, don't assume that they are all happy with the job they did.
You can also turn to the Internet to find out what past clients have to say about the contractors you
are considering. Do some Google searches for things like "" "problems", or
"" "lawsuit" (or "lien", "damages", etc.) and see what comes up.
Check a contractor's license status with your state's licensing board. Visit UP's State by State
Help Section for links to state licensing boards in every state1.
If he/she doesn't have a valid license, find someone else. You can also check with the Better
Business Bureau to get a report on the
contractors you are considering. If he/she is not a member, ask why not.
Your architect can also be a source to find good contractors, but don't just take the architect's
recommendation and stop there. There is a much greater chance that the architect and contractor
will do business together in the future than work with you again. Know that in residential
construction, contractors and architects often look out for each other, to the owner's detriment.
This can range from the contractor paying a "finder's fee" to the architect, to an arrangement
where the contractor will not charge you for correcting the architect's mistakes in exchange for
the architect recommending the contractor's billings for payment. In either event, they are
helping themselves to your money.
We suggest that you develop a final list of three prospective contractors, request from them an
outline of their qualifications and references, and then interview each one. Create an interview
committee made up of you, your architect, and a trustworthy friend in the construction business,
or someone who has been through the rebuilding process him- or herself.
Lesson 2: Bid or Negotiate? Most of the best custom home contractors will not agree to
participate in a simple bid project because they typically have enough business without the hassle
of bidding for it. You can, however, get a good deal on a construction project by "bidding a
negotiated contract". Here is how that works:
Lesson 3: Negotiate the right contract terms. The process of constructing a home is a virtual
orchestra of diverse talents, some working together for the first time, to create something that is
unique, and which has never been assembled in this form before. They are all looking out for
their own interests first, and they all want your money. They all have the objective of getting
considerably more of your money than what it will cost each of them to produce their
contribution to your project. Depending on local economic conditions, there may be a lot of
available contractors or the opposite-demand may exceed supply. Your ability to get the most
for your money will depend on when you are rebuilding, and how well you negotiate the deal.
There is an old saying in construction contracting: "The owner gets to play offense until they
sign the contract, after that they only get to play defense." So make sure you have left yourself
in the best position possible when you sign the contract.
Some tips on negotiating contracts with your contractor:
Lesson 4: Payments to the Contractor. Contractors, subcontractors, and material suppliers who
perform work or send materials to your project have lien rights to your property. If you pay your
general contractor and he or she fails to pay subs and suppliers, those subs and suppliers can put
a lien on your property, and you may have to pay them directly to remove the lien – even if you
have already paid the money for the work to the general contractor. You should periodically
check your county recorder's list2 of "Grantor/Grantee" recordings for any liens, notices, etc. Be
sure to search for different spellings of your name - with/without middle name, middle initial, first
name variants, etc. - sometimes the documents are recorded in strange ways.
There are basically three ways to avoid liens:
Many disaster survivors that UP has helped over the years have told us that although they
followed most of these suggestions, they still wound up with some liens and lawsuits. However,
they were able to prevail through diligence and good record keeping, so it didn't cost them much
more than a lot of time and effort.
Lesson 5: Change Orders. One thing is certain: things will change. The contract provides for a
cost and time for construction based on the construction documents, plans, etc. Changes will
occur primarily due to:
Basically, the contractor is responsible to have made a reasonable anticipation of the requirements of the project. When things occur beyond reasonable anticipation, the contractor is entitled to receive a reasonable adjustment in contract price and time. The work will cost quite a lot more when it occurs due to a changed condition compared to what it would cost when it is purchased as a part of the base contract. Project studies have shown that the premium for change order work will be around 40% or more over base contract work, due to the inefficiencies in buying and administering change order work. Change order work can be avoided by:
When changes do occur, follow the process outlined in the contract for administration of
changes, and make sure all changes are in writing!
Lesson 6: Administering the Process. The AIA contract does a pretty good job of outlining the
process for administering the construction contract. Some architects are good at contract
administration, and some are almost worthless. There are also "owner advocates" or owner's
representatives out there who can help to administer the process. A few key concepts in contract
administration can go a long way in keeping you out of trouble:
Project issues are more like fish than fine wine; they don't improve with age, and only get
stinkier as time goes on. Deal with issues promptly and in writing to keep them from disrupting
and dominating the project.
Volumes have been written and careers have been spent exploring all of the strategic aspects of
construction project management. We have tried to "dispense with the trivial many, in favor of
the critical few" as it relates to staying out of trouble on your home rebuilding project. Most
contractors will hate being asked to prepare written documentation. They will also hate reading
the contracting provisions, and living them as well! We can tell you with certainty that if you
follow the concepts outlined above, your chances for a successful project and your chances of
avoiding litigation will be greatly enhanced.
For related information, read UP's publications:
Xactimate Demystified
Guidelines for Reviewing Adjuster and Contractor Estimates
Sample claim forms in the UP Claim Help Library
These tips were drafted by Ted Bumgardner, president of Xpera Group, a Solana Beach firm that
specializes in construction consulting and forensics, with edits by UP Staff and Amy Bach, Esq.